11.2.1 Crimp connections (unpressed untight)

Unpressed untight connections must be checked with a test
pressure of 0.6 MPa (6 bar) or according to manufacturer's
specifications prior to the actual tightness test. The test time
is 15 minutes.
Connect the pressure sensor to the pipeline to be tested and
start measurement using
.
(CONTINUE)
Connect the external pump to the pipeline using a valve and increase the pressure. If the
test pressure is reached, start the stabilization phase using
.
(CONTINUE)
The stabilization phase can be terminated manually and you
can switch to the measurement manually. The measurement
starts automatically at the end of the stabilization period.
The measurement can be terminated prematurely using
.
(CONTINUE)
The pressure at the beginning of the measurement, the cur-
rent pressure in the pipeline and the already elapsed time of the measurement period are
shown during the measurement.
At the end of the measurement or after premature termina-
tion, a switch to the result display occurs and the documenta-
tion menu can be accessed.

11.2.2 Metal, multi-layer composite and PVC pipes

A stabilization period for temperature equalization amounting
to 10 min and a test time of 30 min must be complied with for
the tightness testing of drinking water installations using wa-
ter, which consist of metal, multi-layer composites and PVC
pipes. The test pressure is 1.1 MPa (11 bar). There can be
no drop in pressure during the test time and there can be no
recognizable leaks.