5 Operate
Preconditions:
The discharging power pack and the ionizing unit are connected and
installed as specified in the operator instructions.
5.1 Normal operation
There is no signal line connected to the signal socket. The jumper
plug must be connected to the signalling socket.
1. Use the power switch to turn on the discharging power pack.
2. The indicator light is lit.
3. The discharging power pack is running.
4. If the operation fails, the indicator light turns off.
5.2 Cyclic operation
The signal line K6 is connected to the K6 signal socket of the
discharging power pack.
1. Use the power switch to turn on the discharging power pack.
2. Use the signal line to switch on the HV.
3. When the HV is switched on, the indicator light illuminates.
4. The discharging power pack is running.
5. If the operation fails, the indicator light turns off.
• To verify this, the power switch is illuminated.
• The HV is switched on.
• In order to correct the malfunction, proceed with
troubleshooting the error. Refer page 14.
• To verify this, the power switch is illuminated.
• Close the external clock switch.
or
• Trigger via the control voltage.
• In order to correct the malfunction, proceed with
troubleshooting the error. Refer page 14.
5
Operate
13