Overview
7HVWLQJ WKH SURWHFWLRQ V\VWHP
2YHUYLHZ
Before start of this process, all individual devices that are involved in the fault clearance
process of the protected object must have been tested as individuals and set in operation.
The breaker must be ready for an open-close-open cycle.
Scheme performance test is the final test that should be carried out before the protected
object is taken into service.
Due to the complexity in combination with already performed tests, it is not necessary
to test all protection functions and all fault types in this process. The most important
protection functions in the terminal for single line to earth fault and phase-phase fault
could be used for the test.
The shaping of the test process is dependent on the complexity of the design of the
switchyard. Hereby follows some items which could be used as guidelines.