MACHINE ASSEMBLY

DANGER! Always use correct lifting devices and NEVER hoist or transfer loads over personnel!
15.
Attach the spreader chains to the lifting eyes on the base push unit making sure that the two
longer chains are attached to the push bar end of the machine. Be sure that the 4-hook roller
assemblies are pinned in the upright position and that the push bar dogs are retracted into the
push bar and pinned into place.
16.
Gently and slowly lift the base push unit. Adjustment of the spreader chains may be necessary
to keep the machine at the same angle as the track.
17.
Slowly lower the base into the bore pit and master track. Keeping the pinion gears lined up with
the rack rear mounted in the track
CAUTION! EQUIPMENT HAZARD! Do not slam or drop the base push unit into the master track.
Pinion gear damage may result.
18.
Attach the spreader chains to the lifting eye of the power package. Use a shackle in the
appropriate lifting hole to lift the sub frame on the same angle as the track and base.
19.
Once the power package angle is adjusted, slowly lower it into the bore pit over the track and
base unit.
20.
Carefully lower the sub frame into the base unit. The power package will align itself as it is
lowered into the base unit. Pay attention to all hosing as the two come together.