ABB GSBK Series Installation And Maintenance Manual page 34

Transformer bushing
Table of Contents

Advertisement

Procedure
1.
Connect the upper draw-rod (1) to the lower
draw-rod (4).
2.
Hold the pull-through cord (12) in tension, while
lowering the bushing onto the transformer.
3.
When installing the bushing at the transformer
factory:
1.
Make sure that the bushing is installed in the
correct orientation.
2.
Make permanent markings (16) on the
bushing flange and the transformer turret.
34
CAUTION!
Do not damage the stud bolts. There is
a risk of metal falling into the
transformer.
NOTE!
Plastic sleeves put on two or three of
the stud bolts will help to guide the
flange, and will prevent damage to the
stud bolts.