Transformer bushing
Table of Contents

Advertisement

Procedure
1.
If the bushing has the optional transport container
installed, remove it.
2.
Put the pull-through cord (12) through the
box-spanner (13).
3.
Apply Vaseline to the threads on the pull-through
cord (12), then connect it to the upper draw rod.
Installation and maintenance guide
1ZSC000563-AAB EN, REV. 6, 2019-09-12
CAUTION!
Do not cause damage to the RIP-core
when removing the transport container.
NOTE!
The terminal on the pull-through cord
(12) has M8 threads.
NOTE!
Or use a lubricant with equal properties
to Vaseline.
29