6 Commissioning

6.1

Commissioning preparation

Commissioning is the last phase necessary to get the Terra DC Wallbox operational. The
purpose is to check the safe functioning of the charger for its operational purpose.
A certified service engineer from the ABB Service department or a trained engineer by
ABB is required to perform the commissioning. During this commissioning, the safety
and the functioning of the charger will be tested.
Before the service engineer can start, the following conditions must be met:
All work described in Preparation, Construction and Placement and connection is
done.
Power is available.
A local technician is present for assistance and to switch on the power.
Internet access must be available in case 2/3G is not functional.
A Combo compliant electric vehicle must be available for testing CCS charging.
A CHAdeMO compliant electric vehicle must be available for testing the
CHAdeMO charging.
Any electric vehicle for instructing the site operator.
Commissioning is executed according to the check list, this check list can be found in
the Helios Suite Service tool that is available to the certified commissioning engineers or
their supervising ABB organization. Also the following data is required for input:
End-user Contact person (Create a contact if it doesn't exist).
Charger address (Check the mentioned address, it will be the address the
charger was shipped to).
Coordinates longitude and latitude for plots on the maps. If there are more
chargers on 1 location, make sure the coordinates are slightly different (at least
0,0001 degrees) to prevent being displayed on the same location.
Site name if this is useful for better recognition (eg Shell petrol station Amster-
dam).
External fuse of the charger.
2 2 -O CT -19
NOTICE
Warranty
It is not allowed to move the Terra DC Wallbox, after it is
commissioned.
In case the Terra DC Wallbox is moved without approval
from ABB, the warranty will be considered void. In case of
relocation please contact the local ABB Service department.