Installing The Outdoor Unit - Huawei NetCol5000-A035 Quick Manual

In-row air cooled smart cooling product
Hide thumbs Also See for NetCol5000-A035:
Table of Contents

Advertisement

1. You are advised to use angle steel, square steel or channel steel. Width of 60 mm and
thickness of 4 mm to 5 mm are recommended.
2. When D (width of angle steel) is more than 60 mm, it is interfering with the cable routing holes.
Cut out the part on the angle steel to avoid interfering. If D is less than or equal to 60 mm, skip
this step.
3. Install a shock absorbed bar (5 mm thick, made of EPDM rubber) on the bottom of the rack.
4. Control the welding process and avoid excessive error.
5. The rack is applicable to the scenario with enclosure frames. After enclosure frames are
installed, holes for the screws installed to secure the rack and unit do not change.
2. Fixing the rack
M12x60 (4 PCS)
4

Installing the Outdoor Unit

Protective cardboard for fins must be removed after installation to protect people from injuries.
45 N•m
3. Securing the smart cooling product on the rack
Secure the smart cooling product on the
rack using four screws removed from the
pallet.
8
M12x80 (4 PCS)
45 N•m