Commissioning

4.1

Safety

Only qualified staff trained by Siemens Building Technologies may prepare
and commission the SEZ220 signal converter.
4.2

Begin commissioning

4.2.1
Initial startup
The commissioning menu automatically starts when AC 24 V operating voltage is
supplied to the signal converter. Note:
During commissioning, the application is not active. The outputs are in a defined
OFF state.
The following settings are displayed as soon as the signal converter is started:
• Access level PASS (Password level).
• COMMIS (Commissioning) menu with flashing menu item PARA (Settings).
PASS
COMMIS
PARA
APPL ID
CONF
TEST
5146Z14
4.2.2
Start from main menu
The COMMIS (Commissioning) menu is active only at the Password level
(Password = 2). If not yet selected, press ESC and OK at the same time to go to
the access level.
When changing from the main menu to commissioning, the user is informed that
the application is deactivated:
PASS
COMMIS
5146Z15
The following happens after you press OK:
• The application is deactivated.
• All outputs are set to a defined OFF state.
• The COMMIS (Commissioning) menu items are displayed, PARA (Settings)
flashes; see picture above under "Basic settings".
• Press + or – to select menu APPL ID (Basic configuration).
SEZ220 signal converter