46 Mechanical installation

Lifting the converter package

Moving the converter on rollers

Do not move the converter on rollers.

Unpacking

Unpack the wind turbine converter when you have moved the converter to its final
installation location, or near it.
1. Cut the attachment clamps with side cutters and pull them away.
2. Remove the fastening screws/nails/rivets and unpack the converter from the wooden
package.
3. Cut the plastic covering the converter with a carpet knife and remove it.
4. Detach the converter from its platform, lift the converter and remove the platform.