Quick installation, commissioning and operation
flowchart
Plan the installation. Check: ambient conditions,
ratings, required external cooling circuit arrangements,
compatibility of the generator, power cable connection,
etc.
Select the cables.
Unpack and check the equipment.
Check the type code indicated on the type designation
label against the original order.
Check that all necessary option modules and
equipment are present and correct.
Only intact converters may be started up!
Check the installation site.
Route the cables.
Move the converter to the installation site and attach it
to the floor.
Connect an external cooling circuit to the converter.
Check the insulation of the generator and the generator
cable.
Connect the power cables. Connect the control and the
auxiliary control cables.
Check the installation.
Commission the converter.
Task
Introduction to the manual 25
See
Technical data,
page
107
Planning the electrical installation,
Option manuals (if optional equipment is included)
Checklist before mechanical
Checklist before mechanical
Routing the cables,
page
Mechanical
installation, page
Cooling and
heating, page
Checking the insulation of the assembly,
Electrical installation,
page
Installation checklist,
page
Start-up guide and firmware manual
page
53
installation, page
44
installation, page
44
61
43
129
page
67
67
77