J304, Audio Line Out Connector - Spectrum Digital TMS320VC5509A EVM PLUS Technical Reference

Table of Contents

Advertisement

Spectrum Digital, Inc

3.4.3 J304, Audio Line Out Connector

The audio line out is a stereo output. The output connector is a 3.5 mm stereo jack. The
signals on the mating plug are shown in the figure below.
3.4.4 J302, Headphone Connector
Connector J4 is a headphone/speaker jack. It can drive standard headphones or a high
impedance speaker directly. The standard 3.5 mm jack is shown in the figure below
.
3-10
Figure 3-4, Audio Line Out Stereo Jack
Figure 3-5, Headphone Jack
TMS320VC5509A EVM PLUS Technical Reference
Ground
Right Line Out
Left Line Out
Ground
Right Headphone
Left Headphone