Installation

Do not instal ICAD must before
welding. This apply for electrical as
well as for mechanical installation.
Please observe that ICAD when
connected to 24 V d.c., will send
out acoustic noise at stand still. This
has no influence on the function/
operation of the ICAD.
Use
ICAD 600, ICAD 900 and ICAD 1200 can be
used together with the following Danfoss
valves (fig. 1, 5a and 5b).
ICAD 600
ICAD 900
ICM 20
ICM 40
ICM 25
ICM 50
ICM 32
ICM 65

Electrical data

Supply voltage is galvanically isolated from
in-/output.
Supply voltage
24 V d.c., +10% / -15%
Load ICAD 600: 1.2 A
ICAD 900: 2.0 A
ICAD 1200: 3.0 A
Fail safe supply
Min. 19 V d.c.
Load ICAD 600: 1.2 A
ICAD 900: 2.0 A
ICAD 1200: 3.0 A
Anolog Input - Current or Voltage
Current
0/4 - 20 mA
Load: 200 W
Voltage
0/2 - 10 V d.c.
Load: 10 kW
Analog Output
0/4 - 20 mA
Load: ≤ 250 W
Digital Input - Digital ON/OFF input by means
of voltfree contact (Signal/Telecom relays
with gold-plated contacts recommended) –
Voltage input used
ON: Contact impedance < 50 W)
OFF: Contact impedance > 100 kW
Digital Output - 3 pcs. NPN transistor output
External supply: 5 - 24 V d.c. (same supply
as for ICAD can be used,
but please note that the
galvanically isolated
system will then be
spoiled).
50 W
Output load:
Load:
Max. 50 mA
Temperature range (ambient)
–30°C/+50°C (–22°F/122°F)
Enclosure
IP 67 (~NEMA 6)
© Danfoss A/S (AC-SMC/MWA), 08-2011
Electrical connection
Connection to ICAD is done via M12
connectors. ICAD has two M12 male
connectors build-in:
Power supply: 4 poled M12 male connector
Control signals: 8 poled M12 male connector
If ICAD is delivered with cables (1.5 m. (60
in.)) M12 female connectors: (Cable set with
M12 female connectors in other lengths are
available)
Power Supply cable with 4 poled M12
female connector
3 x 0.34 mm
I: Black (+) 19 - 24 V d.c. fail safe
II: White (+) 24 V d.c.
III: Brown (–) 24 V d.c.
Control cable with 8 poled M12
ICAD 1200
female connector
7 x 0.25 mm
ICM 40
A: Black (–) Digital output.
ICM 50
ICM 65
B: Brown (–) Digital output.
ICM 100
C: Red
ICM 125
ICM 150
D: Orange (–) GND - Ground.
E: Yellow (+) Analog input
F: Green (+) Analog input 0/2-10 V /
G: Blue
*) If Neutral zone / 3 point control is
selected (parameter i02 = 3) then
E and G is used as DI2 - Digital
ON/OFF input. Se fig. 9.

Electrical installation

General procedure for ICAD 600/900/1200
installed on all ICM valves.
All necessary electrical connections to be
made. Analog or digital operation of ICM
valve.
Fig. 6
Analog operation - 7 wired cable (A-G)
Modulation control. ICM valve to be
controlled from Danfoss electronics,
type EKC (fig. 7), or third party
electronics (like e.g. PLC).
Connect analog input signals. Currrent
(mA) or Voltage (V). See Parameter
list for configuration of analog input
signals.
Yellow (+) and Orange (GND) are used
for current (mA) input.
or
Green (+) and Orange (GND) are used
for Voltage (V) input.
Blue (+) and Orange (GND) are used
for current (mA) output (optional, not
mandatory).
Fig. 6
Digital operation - 7 wired cable (A-G)
ON/OFF ICM solenoid valve operation.
ICM valve to be controlled by means of
a digital voltfree contact.
Connect digital input signals (fig. 8).
See Parameter list for configuration
of digital input signals.
Green (+) and Orange (GND) are
connected to a voltfree contact.
Digital output signals are optional, not
mandatory.
Black (–) and Orange (GND) are
DKRCI.PI.HV0.E6.02 / 520H3832
(3 x ~22 AWG) (fig. 6)
2
supply (optional).
(7 x ~24 AWG) (fig. 7)
2
Common Alarm.
ICM fully open.
(–) Digital output.
ICM fully closed.
0/4-20 mA. *)
DI1 - Digital ON/OFF
input.
(+) Analog output
0/4-20 mA. *)
connected to auxiliary relay for
Common Alarm.
Brown (–) and Orange (GND) are
connected to an auxiliary relay
indicating ICM fully open.
Red (–) and Orange (GND) are
connected to an auxiliary relay
indicating ICM fully closed.
Supply voltage - 3 wired cable (I, II, III)
ICAD must be connected to a normal
24 V d.c. supply. As an option, a fail safe
supply is possible by means of a battery
or UPS (Uninterruptible Power Supply).
When voltage is applied as described
below, ICAD is ready to be configurated.
See Parameter list.
ICAD configuration can be done
independently whether the ICAD is
installed on the ICM valve or not.
See Mechanical installation.
Connect the White (+) and Brown (–)
to a 24 V d.c. supply voltage (fig. 6).
Fail safe supply as an option (not
mandatory).
Connect the Black (+) and Brown (–) to
a fail safe supply.

Mechanical installation

General procedure for ICAD 600/900/1200
installed on all ICM valves (fig. 3).
Check that the three socket set screws
are fully unscrewed counter clockwise
with a 2.5 mm Hexagon key.
Mount ICAD by slowly lowering it on
top of the ICM valve.
The magnet coupling will drag the ICM
and ICAD together and in position.
Push ICAD in place.
Fasten ICM and ICAD with the three
socket set screws using a 2.5 mm
Hexagon key.
Special moisture seal is damaged if
screws are removed (fig. 3, pos. A)
Neutral zone / 3 point control (fig. 9)
¡02 = 3
When ¡02 = 3 the speed given by ¡04
(opening) and i14 (closing) are active
When ¡02 = 3 the factory setting of ¡04
(opening) and ¡14 (closing) are both set to
10.
¡13 (Inverse operation) is active
¡16 = 1 (Encoder operation enable) is active.
¡13 = 0 (Direct operation)
DI1 = DI2 = OFF
ICAD/ICM maintain current position
DI1 = DI2 = ON
ICAD/ICM maintain current position
DI1 = ON, DI2 = OFF
ICAD increase opening degree
DI1 = OFF, DI2 = ON
ICAD decrease opening degree
¡13 = 1 (Inverse operation)
DI1 = DI2 = OFF
ICAD maintain current position
DI1 = DI2=ON
ICAD maintain current position
DI1 = ON, DI2 = OFF
ICAD decrease opening degree
DI1 = OFF, DI2 = ON
ICAD increase opening degree
3