Maintenance Procedures

After Each Use

Clean the thermowell by wiping with a dry, lint-free cloth.
If cleavagae was performed, clean the Product lines.
Connect a 50 mL centrifuge tube to the product position.
Open the reaction vessel and add ~20 mL dichloromethane to the reaction vessel. Close the
reaction vessel.
With the pump turned on, turn the right knob to "Product" to drain the dichloromethane into
the centrifuge tube.
Repeat with an additional 20 mL dichloromethane.

Monthly Maintenance

Replace the dip tube filters in the main solvent and deprotection bottles.

Semiannual Maintenance

Replace the Wash Solvent with methanol and perform a wash of the reaction vessel.
Replace the frit on the bottom of the reaction vessel.
Replacement of Reaction Vessel Frit
1. Remove the drain line from the bottom of the reaction vessel.
2. Open the reaction vessel by pressing up into the reaction vessel top and rotating.
16
Discover Bio
Manual Microwave Peptide Synthesizer
600423 • Revision 2 • August 2017

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Discover Bio and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Table of Contents