Installation Procedure
3. Refer to
Figure
11. Remove cable W50 connecting A3 Digital IF J17 to A16 Reference
Assembly J726. Note cable routing from Digital IF J17 through the opening in the side panel.
This cable will not be reused.
4. Remove cable W38 connecting A15 Front End Controller J901 to A3 Digital IF J15. Note cable
routing from Digital IF J15 through the attenuator brackets and switches. This cable will not be
reused.
Figure 11
A3 Digital IF Assembly Cables
20