Pre-installation checklist

Table 7 Checklist before installation
Item
Installation
site
Slide rails and chassis rails
Requirements
Ventilation
Temperature
Relative humidity
Cleanness
ESD prevention
EMI prevention
Lightning
protection
Verify that the power system at the installation site meets the
Power supply
requirements of the power modules, including the input method and
rated input voltage.
Mounting brackets with
cable management
brackets
There is a minimum clearance of 100 mm (3.94 in) around the inlet
and outlet air vents for heat dissipation of the firewall chassis.
A ventilation system is available at the installation site.
Operating:
Without hard disks: 0°C to 45°C (32°F to 113°F)
With hard disks: 5°C to 40°C (41°F to 104°F)
Storage: –40°C to +70°C (–40°F to +158°F)
Operating:
Without hard disks: 5% RH to 95% RH, noncondensing
With hard disks: 10% RH to 80% RH, noncondensing
Storage:
Without hard disks: 5% RH to 95% RH, noncondensing
With hard disks: 5% RH to 90% RH, noncondensing
Dust concentration ≤ 3 × 104 particles/m3
No dust on desk within three days
The firewall and the rack are reliably grounded.
The equipment room is dust-proof.
The humidity and temperature are at an acceptable level.
Always wear ESD clothing, ESD gloves, and an ESD wrist strap
and when you install and remove a transceiver module.
Put the removed interface modules on an ESD workbench, with the
PCB upward, or put them in ESD bags for future use.
Take effective measures to protect the power system from the
power grid system.
Separate the protection ground of the firewall from the grounding
device or lightning protection grounding device as far as possible.
Keep the firewall far away from radio stations, radar and
high-frequency devices working in high current.
Use electromagnetic shielding when necessary.
The grounding cable of the chassis is reliably grounded.
The grounding terminal of the AC power receptacle is reliably
grounded.
(Optional) A power lightning arrester is installed.
7