Hardware Installation
5895XL installation involves the following steps:
AC power (Section 3.1) and backup battery connection (Section 3.2).
Physical connection to the FACP or to the controlling 5895XL (see Section 3.3).
Setting an ID for the 5895XL (Section 3.3.1).
Physical connection of SBUS modules that will be powered by this 5895XL (Section 3.4).
Physical connection of any outputs (conventional relays, notification appliances, auxiliary power modules, and so on) that will be
powered by this 5895XL. See Section 3.5.1 for notification appliance wiring information. Refer to the FACP Installation Manual,
for software configuration information and other information about installing outputs.

3.1 AC Power

At installation, connect the AC terminals to 120 VAC source as shown in Figure 3.5. It may be necessary for a professional electrician to
make this connection.
The AC terminals are rated as 120 VAC, 50 or 60 Hz, 2.7 A.

3.2 Battery Connection

The 5895XL battery charge capacity is 7.0 to 33.0 AH. Use 12V batteries of the same AH rating. Determine the correct AH rating as per
your current load calculation (see Section Table 2.4 or Table 2.5).
NOTE: When your backup batteries requirements use backup batteries that are to large to fit into the 5895XL cabinet. The AB-33 cabinet
holds batteries up to the 33 AH size. (Refer to FACP Installation Manual for AB-33 installation instructions.
* 33AH max battery size for FM (Factory Mutual) installations
18
Section 3: Hardware Installation
Model Number
5820XL/EVS
6820/EVS
5700
6700
5808
6808
To 120 VAC
Power Source
Figure 3.5 AC Power Connection
FACP Installation Manual
LS10061-001SK-E
LS10144-001SK-E
151295
LS10148-001SK-E
151274-L8
LS10146-001SK-E
5895XL Manual - P/N 151142-L8:L 08/09/2017