Setting
Remove the vinyl protective coating from all of the exterior surfaces.
Roll the oven into its final installed position. (You may wish to install the hood before locating the oven.)
Adjust the left front leveling screw until the weight is removed from the wheel assembly. Remove the
wheel assembly.
Adjust the rear leveling screws and the left front leveling screws until the left jamb is level from left to
right and front to back. Lock the left front adjusting screw in place.
Close the loading door. Adjust the right front leveling screw until the gap at the top of the door opening is
even all across. Check the gap along the left side of the door. Recheck the level of the oven.
Loosen the floor clamp screws around the perimeter of the oven floor.
Walk around the stainless floor until it is in full contact with the concrete floor. Retighten the floor clamp
screws.
Drill the floor with a 3/8" diameter drill to accept the concrete floor anchors.
Mark the drill bit at 1-1/2" from the end with tape. Drill until the mark is at the top of the stainless
o
steel floor. Do Not drill too deep.
Clean the holes of concrete dust.
o
If the oven is mounted on stone or ceramic tile, extend the holes and the anchors into the concrete
o
substrate.
Install the anchors in the holes and set in place with the anchor setting tool. (Note: One good solid blow is
better than many little taps.)
Install the #¼-20 flat head screws in the anchors. Use the anchor washers at the holes in the middle of the
floor at the larger anchor holes. Additional screws have been provided in the event that a hole is drilled
too deep
Adjust the Loading door latch to ensure a good seal around the door. Do not over tighten the door.
Check the level of the rack carrier shaft. Place an accurate level on the top of the carrier and rotate the
carrier to the four points of the compass. The level bubble should be in the same position relative to the
carrier when rotated. If not, remove the carrier and level the shaft.
Loosen the four corner screws on the rotator shaft level adjusting plate on the under side of the inner
o
ceiling. Remove the two remaining screws.
Move the shaft manually until the shaft is level in all four directions.
o
Retighten the four corner screws.
o
Drill two new screw holes in the adjusting plate with a #7 drill bit and tap #¼-20. Install the two
o
remaining screws to lock the shaft level in place.
ETL File 3028821
INSTALLATION CONT'D
11
Rev. A 2002