4.3
HOIST-A-MATIC
Opera-GH is designed with a self-engaging chain hoist with one step operation and automatic power cut-off.
No floor level disconnect is required which simplified operation and installation
The standard Opera-GH is provided with a chain hoist located on the right of the operator. If handing requires the
chain hoist to be on the left (rolling doors, left operator hood mounting for ex.), it could easily be transferred from
Right Hand side to Left Hand side in the field.
Final position of the
chain hoist when it is
transferred from Right to
Left hand side
Transferring the chain hoist from right to left or vice versa is done very easily in the field. No extra parts or any
kind of adjustment is required to change the location of the chain hoist. Refer to the above drawing (Figure 10)
STEP BY STEP INSTRUCTION OF TRANSFERRING THE CHAIN HOIST FROM RIGHT TO LEFT
Use an Allen Key to unscrew and remove the Collar 5/8'
Remove the Washer located in between the Collar and the Chain Guide.
Remove the Chain Guide
Remove the Pocket Wheel.
NOTE: Cutter pins are supplied on both sides of the hoist shaft.
Once these parts are removed from the right side of the hoist shaft, refer to the instructions below to mount
the chain hoist on the left side.
Place the Pocket Wheel against the Cutter Pin
Place the Chain Guide
Place the Washer against the Chain Guide
Put the Collar at the end and use an Allen Key to tighten the setscrew
Figure 11
Changing the position of a manual Chain Hoist
10
Cutter pin
Pocket wheel
Chain
guide
Collar 5/8'
OGH hoist
shaft
Washer