Maguire Products, Inc.
VBD® - Vacuum Dryer®
Install Connections
Attach the Heating Hopper
butterfly valve air lines.
The two air lines that connect the
Heating Hopper Air cylinder to the
VBD-150 are different sizes to
prevent an incorrect connection.
Attach the Heating Hopper Hose
Using the 2" Hose Clamp, attached the red Heating Hose
to the Heating Hopper.
Attach the RTD Plugs
The RTD plugs are different sizes and will only install on the
correct outlet.
Installing the Retention Hopper
Unbox the Retention Hopper. The Retention Hopper is
identified by the red handles located on the top of the hopper
(the Vacuum Chamber has red handles on the upper sides).
Close the slide-gate to allow the Retention Hopper to seat
down onto the base of the VBD-150. Once seated open the
slide-gate to allow material to flow.
Install the Retention Hopper so that the Retention Hopper
manual slide-gate is located at the forward right corner of the
Dryer.