Step 8: Checking the Power-Up Test Results

The power-up test can take several minutes to complete, depending on the
number of installed options you have and on which default settings you use:
If the power-up test results on the screen are similar to the results in
Figure 1–1, the system has passed the power-up test. Go to step 9.
If the power-up test results on the screen are not similar to the results in
Figure 1–1, the system has not passed the power-up test. Go to substep 1.
Figure 1–1 Successful Power-Up Test Screen
KA55-A or KA51-A or KA56-A V2.6, VMB 2.15
Performing normal system tests.
74..73..72..71..70..69..68..67..66..65..64..63..62..61..60..59..
58..57..56..55..54..53..52..51..50..49..48..47..46..45..44..43..
42..41..40..39..38..37..36..35..34..33..32..31..30..29..28..27..
26..25..24..23..22..21..20..19..18..17..16..15..14..13..12..11..
10..09..08..07..06..05..04..03..
Tests completed.
>>>
Central Processing Unit (CPU) name, Firmware version number, and
Virtual Memory Boot (VMB) version number
Read-Only Memory (ROM) based diagnostics countdown
Status message
Console prompt
1. Write down the error messages and the error summaries. Figure 1–2
shows an example of an error message and an error summary.
2. Set the on/off switch to the off (O) position.
3. Make sure that all the connections you made in step 3, step 4, step 5, and
step 6 are correct.
4. Set the on/off switch to the on ( | ) position.
5. If an error report is still displayed, see the MicroVAX 3100 Model 85/95/96
Troubleshooting and Diagnostic Information manual.
1–8 Installation Procedure