Thermon Terminator ZP/FAK-1 Installation Procedures

For bulkhead entry of electrically heated tubetrace bundles

Advertisement

Quick Links

Terminator ZP/FAK-1
For Bulkhead Entry of
Electrically Heated
TubeTrace® Bundles
INSTALLATION PROCEDURES

Advertisement

loading
Need help?

Need help?

Do you have a question about the Terminator ZP/FAK-1 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Thermon Terminator ZP/FAK-1

  • Page 1 Terminator ZP/FAK-1 For Bulkhead Entry of Electrically Heated TubeTrace® Bundles INSTALLATION PROCEDURES...
  • Page 2 Terminator ZP/FAK-1 Dimensions The following installation procedures are suggested guidelines for the installation of the Terminator ZP/FAK-1 Bulkhead Entry Kit. Receiving, Storing and Handling 1. Inspect materials for damage incurred during shipping. 2. Report damages to the carrier for settlement.
  • Page 3: Installation Procedures

    INSTALLATION PROCEDURES The Terminator ZP/FAK-1 Split Bulkhead Entry Kit is designed to Installation Precautions make a waterproof seal over the end of TubeTrace and terminate • To minimize the potential for arcing on electrical heat tracing Thermon electric heat trace in an approved junction box. Review and fire caused by product damage or improper installation, Instructions prior to installation.
  • Page 4 Terminator ZP/FAK-1 Mount Screw Silicone and Washers Gasket FAK-1 Top Cover Expediter Base O-Ring FAK-1 FAK-1 Base Bottom Cover Weep Hole Install RTV silicone and gasket, cutting off excess. Mount expediter base with o-ring to FAK-1 Assemble FAK-1 top, tubing bundle, and FAK-1 Apply RTV sealant to both halves.
  • Page 5 Lid will rotate 30°. Thermon • 100 Thermon Dr • PO Box 609 San Marcos, TX 78667-0609 • Phone: 512-396-5801 • 1-800-820-4328 For the Thermon office nearest you visit us at . . . www.thermon.com Form 50079-0219 ©...