SpectraLink Corporation
2.1
Installation Steps and Responsibilities
Task
Description
Site Preparation
Determine location of MCU
Run Cable for System
Run cable to Base Station locations
Pull cable
Terminate cable at Base Station locations
Prepare and install demarc blocks
Assign and program ports
Connect cables to demarc blocks
Install SpectraLink System
Survey site and check components
Install MCUs
Install Base Stations
Install outdoor Base Stations
Connect and register handsets
Set up diagnostic modem
Register handsets
Program handset features
Test handsets
Site certification