Voltage Relay
CONTROL BOXES (CENTRIPRO OR F.E.)
Step 2, Contact Test
1. Meter setting: R x 1.
2. Connections: #1 and #2.
3. Correct meter reading:
Zero for all models.
B. F.E. Blue Relay - Solid State
⁄
– 1 HP QD Control Boxes
1
3
Used from 1994 until present time:
Step 1, Triac Test
1. Meter setting: R x 1,000.
2. Connections: Cap and B terminal.
3. Correct meter reading: Infinity for all
models.
Step 2, Coil Test
1. Meter setting: R x 1.
2. Connections: L1 and B.
3. Correct meter reading:
Zero ohms for all models.
17