The 624 Bld Control Panel; General Description - FAAC 620 Installation Manual

Barrier gate operator/control panel
Hide thumbs Also See for 620:
Table of Contents

Advertisement

P a g e 2 2
T
624 BLD C
HE
G
D
ENERAL
ESCRIPTION
The FAAC 624 BLD control panel is used to operate the
following models.
Barrier gate operators:
620 115VAC/230VAC
640 115VAC/230VAC
The 624 BLD programming controls the following:
Operating logic: A, S, E, EP, B, C and other logics.
Reversing device behavior: Choose whether a
triggered
reversing
immediately reverses gate movement or stops the
gate and reverses gate movement when no longer
triggered.
Torque or Pressure: Adjustable from 0 to 50.
Pause time between opening and closing:
adjustable from 0 to 4 minutes.
Opening/Closing time: adjustable from 0 to 4
minutes.
Deceleration Time: programmable
The 624 BLD control panel is installed in an enclosure
that is conveniently located inside the barrier cabinet.
Any addition enclosures should be rated for outdoor
use and be water proof.
The 624 BLD control panel requires a single-phase
power supply voltage (115 VAC [±10%] or 230 VAC [+6
or -10%], 50–60 Hz). The power supply should be
protected by a 15 amp dedicated circuit breaker (not
provided).
The installer is responsible for grounding the
operator system, for providing the main power
breaker switch, and for making sure that the entire
gate system meets all applicable electrical codes.
The installer should refer to the installation manual
for a given operator for more information.
N
: An installation is U.L. compliant only
OTE
when you install the FAAC operators according
to the UL325 standards.
device
during
closing
6 2 4B LD C ontr ol Pa ne l Ins tal la tion M a nual
ONTROL
I
624 BLD C
NSTALLING THE
Installing the control panel consists of the following
general steps:
Connecting the main power to the control
panel
Connecting the activating device
Connecting the operator to the control panel
Checking the direction of the motor's rotation
Connecting other devices to the control panel
Set operating modes
C
M
P
ONNECT THE
AIN
OWER
P
O
)
ANELS
NLY
WARNING! Turn the main power off before you
make
any
electrical
programming.
If the panel is installed in the barrier system than the
main power needs to be wired to the switch that is
explained in the barrier section of this manual.
Wire the main power supply to control panel terminals
in block J9 (Figure 1C). The installer is responsible for
insuring that a separate, grounded circuit protected by a
circuit breaker is between the control panel and the
main power supply. All wiring should conform to
applicable electrical codes, and all wiring and fittings
should be weatherproof and/or suitable for burial.
Connect the ground to the grounding terminal in block
J9 and connect the power wires to the terminals labeled
N (neutral) and L (line).
N
:
For a 230V system, a neutral is not
OTE
needed. Connect one 115V line to the L (Line)
and a second 115V line to the N (Neutral).
Ja nua ry , 2 00 7
6 2 0 /6 40 O pera tor An d
P
ANEL
P
ONTROL
ANEL
S
(R
UPPLY
EPLACEMENT
connections
or
before

Advertisement

Table of Contents
loading

This manual is also suitable for:

624bld640

Table of Contents