Technical data 1 ~230 V ±15%, 50 / 60 Hz Mains voltage Rated power Max. 6,7 kVA (180 A / 17,2 V) Max. 7,0 kVA (140 A / 25,6 V) Load capacity 35 % ED 180 A / 17,2 V 100 % ED 120 A / 14,8 V 35 % ED...
Block diagram Main circuit card Z001 Control card A001 Net over voltage protection Aux. Voltage development DC-link charging Undervoltage monitoring EMI-filter Over voltage monitoring Primary rectifier Temperature monitoring Energy reserve Solenoid valve control ”Dual-forward”-inverter Fan control Main transformer Power supply control Secondary rectifying Panel card P001 Spark generator card A002...
Connectors Measuring point A. X1, X3 Z001 connectors Power supply voltage 230 Vac Measuring point B. X2/6, X2/12 Connector A001 Measuring point C Primary rectifier Power supply voltage 230 Vac Shunt resistor, (-) Machine body, equipment earth Aux. transformer T002 supply voltage ~230 Vac Aux.
Measurings Measuring point B. Measuring point A. Gate control pulse (X2/6, X2/12), no load Supply voltage, main circuit card Z001 Measuring point C. DC-link charging (primary rectifier)
Control card A001 Operating diagram - Aux. Voltage development - PWM-control - Shunt amplifier - MMA dynamic control - Solenoid valve control - Fan control - Under voltage watch - Overvoltage watch - Overheat watch - Remote/foot control interface - TIG –torch interface - Panel interface - Filtering of control lines...
Setup • You can enter the Setup mode by pressing both arrow keys ( 1 ) for at least five seconds. • The display will show the name of the parameter ( 2 ) and numerical value ( 3 ). •...
Setup functions Name on Parameter Factory Description display value range setting 0 or 1 End current level selection. 1=5A, 0=15% 0 or 1 Open-circuit voltage selection. 1=30V (VRD), 0=95V 0 or 1 Forced stop during downslope with a brief pressing of the switch. 1=On, 0=Off 0,1,2 or 3 Alternative switch logic.
Page 16
Setup functions A = End current level selection With this function you can set the welding current level when the arc will be extinguished. 0 = 15% of the welding current that is used. 1 = minimum current, which is 5 amperes in this power source. B = Open-circuit selection With this function you can change the open-circuit voltage.
Page 17
Setup functions h = Minimum setting for pre-gas time With this function you can set the pre-gas minimum time to the desired value in the range 0 – 2 seconds.The factory setting is 0 seconds. J = Minumum setting for post-gas time With this function you can set the post-gas minimum time to the desired value in the range 0 –...
Error codes E2: Power source undervoltage The machine has stopped because it has detected a mains undervoltage that disturbs welding. Check the quality of the supply network. E3: Power source overvoltage The machine has stopped the welding because it has detected momentary voltage spikes or continuous overvoltage dangerous to the machine in the electric network.
Power semiconductor testing and replacing A separate discrete-IGBTs can be tested only when disconnected from the board with IGBT-tester. When replacing damaged IGBTs, the whole set has to be replaced, including gate resistors!! Discrete-IGBT and secondary diodes tightening torque to the heat sink is 0,6…1,2 Nm.
Programming 1. Start DataMaster II and press Menu. 2. Select Renesas Programming using UART mode. 3. Use the up and down arrows to choose the program you want to download. 4. Press START on the DataMaster II keypad to start the updating process. 5.
Troubleshooting Problem Possible cause Remedy The power doesn’t start Aux transformer T002 Chech aux. Transformer T002 Panels signal light (green) is not ignited Secondary voltage between connectors X8/1-X8/2. (approx. 23 Vac) Control card A001 If aux. Transformer secondary voltage Is approx. 23 Vac, then replace control card A001 Th net fuses blow when starting Faulty primary circuit semiconductor...