4 INSTALLATION
4.1 Inspection
Upon receiving a DCF Optimized Rack System, examine the packaging for any signs of mishandling or
damage. If any damage is noted, notify your local Vertiv™ representative and your carrier immediately.
4.2 Required Setup equipment
The DCF ships with the tools necessary to adjust supplied components:
•
cage-nut tool
•
13/14-mm wrench
•
combination T30 Torx L-key with Phillips head
The following tools are also required to set up a DCF:
•
pallet jack or forklift
•
utility knife or scissors
•
14-mm socket and ratchet or 14-mm wrench
4.3 Unloading the DCF Rack
Before unloading, note the weight of the model (see Specifications.
CAUTION: Use at least two people when moving the unit.
1.
Using a pallet jack or forklift, move the DCF on its pallet to the installation location.
2. Cut the shrink wrap and remove all packaging.
3. Use a 14-mm socket or a 14-mm wrench to remove the 4 lag bolts that secure the 2 anchor
brackets to the shipping pallet, one in the front and one at the rear of the rack. Each bracket is
secured by four bolts.
•
If the brackets will be used to anchor the rack to the floor, leave them attached to the
rack. If not, removed them.
4. Use a pallet jack or forklift to raise the DCF off the shipping pallet.
5. Slide the shipping pallet out from under the rack.