Commissioning

8
Commissioning
RISK OF FATAL INJURY
from escaping flue gases.
WARNING!
Before commissioning the boiler or the
neutralizer unit, pour approx. 3 gal
(10 liters) of water into the boiler clean-
ing access port or combustion chamber
so as to fill the neutralizer unit and pre-
vent escaping of flue gases through the
boiler condensate trap.
RISK OF BOILER DAMAGE
from corrosion and sludge.
CAUTION!
Before filling, is essential to flush the en-
tire heating system. In order to prevent
sludge and corrosion, the quality of the
first-fill and replenishment water must be
tested (refer to supplementary sheet
"Water treatment...").
USER NOTE
Follow the installation instructions for the
neutralizer unit.
Commissioning should be carried out ac-
cording to the operating instructions for the
boiler, the burner and the electronic heating
system controls.
When commissioning the system and hand-
ing it over to the operator, explain how the
system works and how to operate it, and
hand over all technical documentation.
Draw attention to special servicing consider-
ations and recommend that a maintenance
contract is signed.