Repeat step 29 on other chain master link.
30.
Make sure that drive roller sprockets engage
31.
proper links on both chains. A twisted or misaligned
conveyor will malfunction.
Adjust belt tension as per section 6.3.1 (adjusting
32.
belt tension).
After belt tension is adjusted, run belt to make sure
33.
that it moves as required. On dual sided machine
check belt movement towards left as well as to
right. Check for any sign of malfunction and make
correction as required.
Before reinstalling sideboard rubber assemblies
34.
make sure there is no wear on all four sideboard
rubber seals. If inner sideboard rubber assemblies
(AB) are worn, replace them with new ones. On
outer sideboard assemblies if there is excessive
wear then rubber seal (AC) may have to be
replaced.
www.roadwidener.com
The sideboard rubber seals reduce excessive
35.
conveyor belt wear by preventing debris from
getting into conveyor mechanism. A good fit for
these rubber seals is when seal rubber just makes
contact with conveyor belt.
Reinstall both left and right end-gates assemblies
36.
(D) on respective discharge ends. Use a suitable
lifting device to lift and move end-gate assemblies.
Adjust position of belt wiper frame assemblies (J)
37.
on discharge end by adjusting the screw (I). On
dual sided machine, perform this step on both
discharge ends. The right position for belt scraper
is when the wiper rubber just makes contact with
the conveyor belt.
On dual sided machine, reinstall hopper bib
38.
assemblies (C) on both discharge ends. On single
sided machine, reinstall the bib assembly and end
plate on non-discharge end.
Periodic inspection of conveyor belt and hinge for
39.
wear can save time & money. This also avoids
catastrophic failures of belt.
6.3.3 C
B
onveyor
elt
Following guidelines are provided for better conveyor
belt maintenance.
6.3.3.1 Belt Tension
Specific instructions for consistent belt tension follow.
When Sideboard Rubbers Are Removed And Chain
Is Accessible
After installing conveyor belt, adjust take up bearings
on both sides until chain can be lifted up approximately
1-3/4 inches at center of machine. Then tighten jam
nuts.