3 Commissioning Process
3.6.1 Location Update Test
The test procedure is as follows:
Step 1 Define a test MS in the HLR.
Step 2 Ensure that the network data is correctly configured.
Step 3 Switch on the MS.
Step 4 Start the Abis interface tracing on the BAM by using the LMT.
Step 5 Observe the signaling on the Abis interface and check if either of the following cases occurs:
----End
3.6.2 BTS Coverage Test
The test procedure is as follows:
Step 1 Define a test CDMA MS in the HLR.
Step 2 Select a proper road to carry out a drive test in the BTS coverage area.
Step 3 Record test data, including:
Step 4 Check that the test result conforms to the requirements of engineering design documents.
----End
3.6.3 MS Call Test
The test procedure is as follows:
Step 1 Register two test MSs in the HLR.
Step 2 Power on the two MSs so that they connect to the network and they switch to idle mode.
Step 3 Carry out the following call tests.
3-28
MS call test
Handoff test
Short message service test
Mobile-originated packet data call test
Mobile-terminated packet data call test
The network side accepts the location update.
The network side rejects the location update request.
Tested BTS
Coverage area
Sector
Distance
Signal strength and voice quality
Make a call from one MS to the other and hook on after the conversation.
Huawei Technologies Proprietary
Airbridge BTS3606E&3606AE
System Commissioning Guide
Issue 02 (2006-10-10)
Need help?
Do you have a question about the Airbridge BTS3606E and is the answer not in the manual?
Questions and answers