3 Commissioning Process
3.4 O&M Test
Unless otherwise specified, carry out the following tasks at the BAM side.
Before the O&M test, ensure that the CCPM/CECM and the CMTR/OMTR works normally.
3.4.1 Querying Basic Information of the BTS
To query the basic information of the BTS, do as follows:
Step 1 Enter the following command:
LST BSCBTSINF
Step 2 Click
Step 3 Specify the values of the parameters.
For example: LST BSCBTSINF: BTSID=1;
Step 4 Click
----End
3.4.2 Querying BTS Board Version
To query the BTS board version, do as follows:
Step 1 Enter the following command:
DSP CBTSBRDVER
Step 2 Click
Step 3 Specify the values of the parameters.
For example: DSP CBTSBRDVER: BTSNAME="BTS", BTSID=1, BRDTP=BCKM,
BRDID=0;
Step 4 Click
----End
3.4.3 Verifying the Software Version
To verify the software version, do as follows:
3-18
or press Enter.
or press F9 to execute the command.
or press Enter.
or press F9 to execute the command.
The command CHK CBTSSWVER is used only for verifying the consistency between the running
software version of the BTS boards and the BAM version.
Huawei Technologies Proprietary
Airbridge BTS3606E&3606AE
System Commissioning Guide
Issue 02 (2006-10-10)
Need help?
Do you have a question about the Airbridge BTS3606E and is the answer not in the manual?
Questions and answers