1 Commissioning Preparations
1.1 BTS Equipment
Before commissioning, ensure that:
1.2 Tools for Commissioning
Table 1-1 lists the tools for BTS commissioning.
Table 1-1 Tools for BTS commissioning
Tool
CDMA MS
Qualcomm CAIT or a BLUEROSE
RS NRT-Z44 power meter
SiteMaster 331A
30 dB low-power coaxial attenuator
20 dB low-power coaxial attenuator
DIN-male to N-female adapter
1.3 Personnel
Huawei technical support engineers and the engineers representing the customers complete
the system commissioning together. The customer representative should sign the acceptance
list after the commissioning is complete.
1.4 Site Information
To facilitate the preparation of commissioning tools and commissioning schemes, collect the
following basic information before you start the commissioning of the BTS:
1-2
The cabinet and its components are installed correctly.
The antenna system is installed and connected.
The transmission equipment is connected.
The BTS O&M software and operational software are installed.
The power system is installed.
The equipment for monitoring the equipment room environment is installed. (optional)
BTS ID
Huawei Technologies Proprietary
Airbridge BTS3606E&3606AE
System Commissioning Guide
Quantity
Remark
Two
Mandatory
One
Mandatory
One
Optional
One
Mandatory
One
Optional
Two
Optional
One
Optional
Issue 02 (2006-10-10)
Need help?
Do you have a question about the Airbridge BTS3606E and is the answer not in the manual?