Samsung LH008IWJ Series Installation Manual
Samsung LH008IWJ Series Installation Manual

Samsung LH008IWJ Series Installation Manual

Hide thumbs Also See for LH008IWJ Series:

Advertisement

Samsung Electronics
LED Display
Installation Manual
LH008IWJ*** (P0.84)
SNOW-18010U
Ver. 1.4

Advertisement

Table of Contents
loading

Summary of Contents for Samsung LH008IWJ Series

  • Page 1 Samsung Electronics LED Display Installation Manual LH008IWJ*** (P0.84) SNOW-18010U Ver. 1.4...
  • Page 2 Check first before Installation (1/2) Samsung Electronics • All Power cables and OCM cable must be connected firmly • For HDBT signal stability, use the cable above CAT6 *STP, *FTP level. ( Length 15m~100m ) “CAT6 UTP can not be allowed”...
  • Page 3 Check first before Installation (2/2) Samsung Electronics • Install the device only using SNOW-1810U and its supplied IG. ※ Please check below Cabinet and S-box compatibility table information S-Box SNOW-1810U SNOW-1703ULD SNOW-1703U BN91-20525A BN91-19993A BN91-19100A Cabinet IF015H, IF015H, IF015H, IF020H,...
  • Page 4: Table Of Contents

    Table of Contents Samsung Electronics Product Information and Precautions for Installation Check Point about the Radiant Heat Preparation for Cabinet Installation Frame Installation Cabinet + Frame Installation 6. Disassembly & Front Service S-BOX Installation and Connection Settings and How to Use Issue and Solution 10.
  • Page 5: Product Information And Precautions For Installation

    1. Product Information and Samsung Electronics Precautions for Installation ◇ Frame Kit Composition (Refer to Page 16) Frame Kit Composition Note VG-LFJ08SWW (1 Set) VG-LFJ08FWW FHD Installation (4 Set) VG-LFJ08TWW (9 Set) VG-LFJ08UWW <3x3> <4x4> (16 Set) UHD Installation <1x1>...
  • Page 6 1. Product Information and Samsung Electronics Precautions for Installation ◇ Storage Condition Condition Value Recommend Temperature -20℃ ~ +45℃ -20℃ ~ +45℃ Humidity 5~95% 5~65% Hight 3000m 3000m ◇ Pre-heating Process should be conducted before installation& operation after storage. (refer to page 18)
  • Page 7 1. Product Information and Samsung Electronics Precautions for Installation • Precautions for Installation (LED damage) Caution Image [ Beware of Outside Impact, Fall] ① Beware not to cause any impact on the LED screen or drop the product on the floor MODULE after the protection gets taken off for installation.
  • Page 8 1. Product Information and Samsung Electronics Precautions for Installation ◇ Caution for cleaning screen ★Caution★ - Watch out for damage when cleaning gap between Half- Cabinets - Watch out for damage when cleaning gap between Modules - Do not insert any cleaning tool or spay cleaner directly into...
  • Page 9 1. Product Information and Samsung Electronics Precautions for Installation • Preparations for Installation • Provided in accessory kit. (CY-WJJPWP). (-) (+) driver Adjustment tool MAGNET JIG GAP-TOOL (BN81-17112A) (BN81-17114A) (BN81-17113A) • Provided in Frame Kit. (VG-LFJ08*WW). Absorber Hex Wrench PLIER...
  • Page 10: Check Point About The Radiant Heat

    Written under ‘Video, (back light 10)’ standard  Standard and condition for indoor installation - Standard for using ‘SAMSUNG WALL MOUNT’ (Fulfill ADA) ※ ADA(American’s with Disabilities Act ∙ The gap between the front of a product and a wall: 98.6mm ∙...
  • Page 11 2. Check Point about the Radiant Heat Samsung Electronics  Minimum spacing for buried installation (Specification for no Fan & Samsung Frame Kit installation) Air vent area Min 500mm (ceiling) Min 60mm Airvent area Min 60mm Min 60mm Min 60mm...
  • Page 12 2. Check Point about the Radiant Heat Samsung Electronics  Minimum spacing for wall installation (Specification for no Fan & Samsung Frame Kit installation) Min 500mm (ceiling) Airvent area Airvent area Airvent area Airvent area Min 300mm (floor) Min 90mm...
  • Page 13 2. Check Point about the Radiant Heat Samsung Electronics ◇ FAN Using condition ◇ Vent specification - Air Vent : install at bottom  Using over 70% open ratio vent - Top: Seal except fan hole �� �� �� �� ����. ���� �������� ℎ������...
  • Page 14 2. Check Point about the Radiant Heat Samsung Electronics  Under 30℃ Guidance ※ SAMSUNG WALL MOUNT , Full white, back light 7, VENT 60% unnecessary Rows...
  • Page 15: Preparation For Cabinet Installation

    3. Preparation for Cabinet Installation Samsung Electronics • Preparations Before Installation ① Remove the Box tape at the upper area and then open up the box. (Fig.2) ② Remove the Top–Cushion and hold the handle inside PE-Bag and pull out the set then remove PE bag.
  • Page 16 3. Preparation for Cabinet Installation Samsung Electronics ④ Unfasten the 4 screws on the Cover Corner area to separate those screws and Remove the protective sheet attached to the two sides (Top/Bottom). (Fig.4) SCREW-MACHINE (6003-000133) SCREW Fig.4 Cover Corner Removal...
  • Page 17 3. Preparation for Cabinet Installation Samsung Electronics ◈ Reference : Process of Dehumidification TOGGLE SWITCH SWITCH POWER INLET POWER OUTLET TOGGLE SWITCH ※ Caution: 1. IWJ (LH008IWJ Doesn’t Power On in STB mode(switch) When you install IWJ, please switch to O mode 2.
  • Page 18 3. Preparation for Cabinet Installation Samsung Electronics ◈ Reference : Process of Dehumidification - The Dehumidification process progresses automatically for 24 hours as the brightness increases gradually. Step condition Brightness Time Lighting up display with 10 gray scale 2 hr...
  • Page 19 3. Preparation for Cabinet Installation Samsung Electronics ◈ Reference : Process of Screen check TOGGLE SWITCH SWITCH POWER INLET POWER OUTLET TOGGLE SWITCH 화면 검사 사진 확인 Check the picture of the screen ◈ Internal white pattern 1. After turn on power, press the toggle swtich button for five seconds 2.
  • Page 20 3. Preparation for Cabinet Installation Samsung Electronics ◈ Reference : Power system design Power 3 Power 1 Power 2 Power 1 Power 2 I/G #1 I/G #2 I/G #1 I/G #2 I/G #3 I/G #4 I/G #3 I/G #4 ◈ Power system design 1.
  • Page 21: Frame Installation

    4. Frame Installation Samsung Electronics ◇ Frame Kit Composition. ⓑ ⓒ ⓑ ⓐ VG-LFJ08SWW VG-LFJ08FWW VG-LFJ08TWW VG-LFJ08UWW Item Units Units Units Units ⓐ BRACKET H (horizontal) ⓑ BRACKET SIDE (vertical) ⓒ BRACKET MIDDLE (vertical) ⓓ JOINT H ⓔ JOINT V ⓓ...
  • Page 22 4. Frame Installation Samsung Electronics ① Assemble Bracket Side/Middle with Bracket H. - First insert ⓐBracket H to assembled Joint H and Bracket H. (Fig.1) - Second put 3 groups of Bracket H on ground. And insert Bracket Side/Middle to Bracket H. (Fig.2) .
  • Page 23 4. Frame Installation Samsung Electronics ② Assemble Leveler on the Bracket Side at required height position. - Put Leveler on Bracket side at required height position with moving up and down. (Fig.1) M4 Screw Fig.1 Assemble Leveler...
  • Page 24 4. Frame Installation Samsung Electronics ③ Install assembled Frame on the wall. - After put assembled Frame on the wall, fasten 1 point at center-top which is closest hole with BRACKET H. By using Leveler, adjust horizontal level of Frame.
  • Page 25 4. Frame Installation Samsung Electronics - Fasten 7 points which are closest hole with Bracket V with using more screws. (Fig.3) - It may need more fastening screw according to wall condition. - After fastening, remove the Leveler. Concrete Wall Wood Stud Wall Fig.3 Fix Frame with screw...
  • Page 26 4. Frame Installation Samsung Electronics ※ Precautions for Fastening the Screws...
  • Page 27 4. Frame Installation Samsung Electronics ※ Extent Frame Installation to Horizontal / Vertical. - Assemble Joint C / Joint V into second assembled Frame. Fastening Fastening <Horizontal Extension> <Vertical Extension> - Insert the second FRAME to first FRAME. <Horizontal Extension>...
  • Page 28 4. Frame Installation Samsung Electronics ※ Extent Frame Installation to Horizontal - Mount the Jig by connecting first frame to second frame. And fasten screws. Fastening <Horizontal Extension> Fastening <Vertical Extension>...
  • Page 29: Cabinet + Frame Installation

    5. Cabinet + Frame Installation Samsung Electronics • Fix I/G Location Install I/G first on the back side of the Cabinet of each Type (Fig.1) ※ Location to Install: Locate the I/G at the point 50~55mm below, which is the standard for carving at the right side of the frame, and then fasten the screws.(Fig.2)
  • Page 30 5. Cabinet + Frame Installation Samsung Electronics • Install main body to Frame ① After installing Frame and I/G, install cabinets on the bottom line first ※ Refer to the order of installing cabinets. (Bottom to top, Center to side.) (Fig.1)
  • Page 31 5. Cabinet + Frame Installation Samsung Electronics ④ When installing from second cabinet cabinet to other side ① ②. . First, move modules of 1 cabinet to reverse side ③ ④. . Second, move modules of 2 cabinet to Frame ⑤ as doing with first cabinet.
  • Page 32 5. Cabinet + Frame Installation Samsung Electronics ⑤ After installing first row, assemble Cover PCB at bottom line of cabinets. (Refer to Page 33 for assembly of Cover PCB) . Adjust pixel alignment by fastening screw from Cover PCB. Cover PCB...
  • Page 33 5. Cabinet + Frame Installation Samsung Electronics • Adjust Z-leveling between modules. Each module block can be adjusted its leveling at 4 corner points [Fig.1]. Follow the below step to adjust the level between modules: ① Check the level of modules at corner points of modules and define which module needed to be adjusted.[Fig.2]...
  • Page 34 5. Cabinet + Frame Installation Samsung Electronics • Adjust Z-leveling between modules. 1. Attach Suction-Pad (Refer to P37) 2. Move Module 2.0mm 3. Insert Gap-Tool Turn Gap-Tool 90degree 2.0mm Un-Lock Lock ~2mm 90° 5. Hold Module by Hand Turn Gap-Tool 90degree, Remove Gap-Tool 4.
  • Page 35 5. Cabinet + Frame Installation Samsung Electronics • Align modules in X,Y direction Modules are aligned by Cover PCB which attached on boundary area. * Only do modules alignment after adjust leveling of modules. ① Assemble all Cover PCB to 4 edge by M3L5 screw [Fig.1]. The set screws M4L5 must be assembled slightly and fix later.
  • Page 36 6. Disassembly & Front Service Samsung Electronics Caution ◆ : SMPS Discharge Grab point : - Before you touch or remove the SMPS, touch the two Touchable Area without additional discharging process) discharge points using a discharge Jig to verify the SMPS is full discharged.
  • Page 37 6. Disassembly & Front Service Samsung Electronics 0. Disassemble bezel and Cover PCB (Refer to page 81 & 33) Bezel GAP SHEET Vertical center line Cover PCB Horizontal center line M3L5 M4L5...
  • Page 38 6. Disassembly & Front Service Samsung Electronics Absorber Lock Un-Lock ※ Absorber : Handle type tool that fixed on cabinet front side(LED side) to prevent damage to LED Modules while assembly/disassembly, moving half- cabinets. ※ Handle should be locked in vertical.
  • Page 39 6. Disassembly & Front Service Samsung Electronics ★Caution★ Cannot use Magnet JIG of other LED display model. (weak magnetic force) 0. Magnet Jig Use proper Magnet JIG matching with specification. 1. Access carefully on 45° not to damage modules. (Do not contact Jig to module, 1cm apart) ※...
  • Page 40 Disassembly & Front Service Samsung Electronics Half-Cabinet disassembly • ① Based on the Half-Cabinets to be replaced, the Half-cabinets on the left/right and top should be pushed outward. (Edge Protection is needed. Refer to the Next) ※ UHD Screen (16Cabinet / 32 half-cabinet) Repairing Half- Cabinet ②...
  • Page 41 Disassembly & Front Service Samsung Electronics • Edge Protection Push cabinets toward outside to get 2mm gap that located on same vertical line with repairing Half-cabinet ※ Cover PCB should be removed. ※ pushing order is important. Follow the numbers ※...
  • Page 42 Disassembly & Front Service Samsung Electronics Edge Protection • ★Caution★ Be careful not to damage module ③ Insert GAP Tool at middle of Top/Bottom edge of half- cabinet to fix gap. A/S-ASSY GAP TOOL ※ Insert horizontally, turn vertically and fix.
  • Page 43: Disassembly & Front Service

    Disassembly & Front Service Samsung Electronics Removing cable and disassemble Half-Cabinet • ⑤ Identify location of cables need to be removed. ※ Refer to the TCON board picture. (top : Master / bottom : Slave) ※ Remove the cables close to each other.
  • Page 44 Disassembly & Front Service Samsung Electronics Removing cable and disassemble Half-Cabinet – Using PLIER JIG • ■ Using PLIER JIG, remove 26P Power Cable(SMPS, Redundancy) ※ There is a groove that takes locking on the top head. ※ Locking can slip if it does not get to the groove correctly A/S-ASSY PLIER JIG ※...
  • Page 45 Disassembly & Front Service Samsung Electronics Changing to new Half-Cabinet • ※ New cabinet must be changed after conduct Dehumidifying mode Aging. (Refer to page 100) ⑦ Remove Cover corner from Buffer Cabinet laid on the floor and lift up half-cabinet with absorber attached.
  • Page 46 6. Disassembly & Front Service Samsung Electronics Remove Cable and screw • ① Remove Cover Terminal. Cover terminal Screw point Remove Cover Terminal first since this screw Point is concealed. ※ Note that Master Cover terminal has switch on it.
  • Page 47 6. Disassembly & Front Service Samsung Electronics Remove Cable and screw • ② Remove cable and screw of TCON Board. ※ FFC Cable ※ rear side of half-cabinet Lift up lock and pull out to remove cable. ※ Power Cable...
  • Page 48 6. Disassembly & Front Service Samsung Electronics • Remove and Change TCON Board ③ Remove TCON Board and replace it. ④ Assembly is reverse order of disassembly. ※ The Gap pad is attached to the TCON or Bracket-PCB, so don’t skip when replacing new board.
  • Page 49 6. Disassembly & Front Service Samsung Electronics • Module (Half-cabinet Module) Store & Packaging ① Repairing Half-cabinet should be stored with buffer cabinet. ※ Repairing Half-Cabinet Dissemble Half-Cabinet from existing Buffer Cabinet Change it with Repairing Half-cabinet ※ Repairing Half-Cabinet ※...
  • Page 50 6. Disassembly & Front Service Samsung Electronics • Module (Half-cabinet Module) Store & Packaging ※ Module (Half-Cabinet module) (front/rear) ③ ※ Remove repairing half-cabinet from stored buffer cabinet. ※ Remove repairing half-cabinet from buffer cabinet ④ Package Half-cabinet in The Wall LED Module BOX.
  • Page 51 6. Disassembly & Front Service Samsung Electronics SMPS disassembly • ① Remove screws over the insulator on SMPS. (6EA) ② Remove AC INLET Cable connected to SMPS. (Do not remove 26pin Power Cable yet) ★ Caution ★ Do not touch except marked spot.
  • Page 52 6. Disassembly & Front Service Samsung Electronics SMPS disassembly • ③ Hold 26pin Power Cable and bottom of SMPS. ④ Lift up the bottom part and pull down to separate. Be careful of protruding part at top of SMPS shield.
  • Page 53 7. Cable Connection Samsung Electronics 7-1 Cable Connection • If using 110V, you can connect at most 2 IWJ(IW008J) devices. • If using 220V, you can connect at most 4 IWJ(IW008J) devices. • Exceeding the recommended maximum number of devices can cause the circuit breaker of the product to trigger due to overload.
  • Page 54 7. Cable Connection Samsung Electronics 7-2. The caution for Cabinet installation and Cable connection(Full Front) 1) The set installation order Must be Center to Left/Right direction. → The set installation order and The cable connection order are different. 2) After installing cabinets one line is complete, make sure the connection is OK by connecting OCM/Power cable.
  • Page 55 7. Cable Connection Samsung Electronics 7-3 The direction for Cabinet installation 1) Installation of First row cabinet starts at the bottom of Left-end. 2) After installing cabinets one line is complete, make sure the connection is OK by connecting OCM/Power cable. Then, Install next line.
  • Page 56 7. Cable Connection Samsung Electronics Cable Connection : Data flow standard ◎ Connect OCM cable Forward direction Case 1: Reverse internal Link internal Link ID:2 internal Link internal Link Forward...
  • Page 57 7. Cable Connection Samsung Electronics Cable Connection : Data flow standard ◎ Connect OCM cable Forward direction Case 2: internal Link internal Link Reverse internal Link internal Link Forward ID:2...
  • Page 58 7. Cable Connection Samsung Electronics 7-5 Cable Connection : OCM cable installation standard ◎ Whenever one number of cabinet gets installed, connect necessary cable for each. P0.84 FHD DATA OUT DATA OUT DATA IN DATA IN DATA OUT DATA IN...
  • Page 59 7. Cable Connection Samsung Electronics ◎ Apply COVER CAP to POWER IN CABLE of the top cabinets. COVER-CAP POWER-IN CABLE COVER-CAP 4*4 (Example)
  • Page 60: S-Box Installation And Connection

    8. S-BOX Installation and Connection Samsung Electronics • S-BOX Installation Precautions ① Product recommend installing this product in a standard 19-inch server rack. ② Install ventilation opening, do not install the vent by turning it sideways or upside down ③...
  • Page 61 8. S-BOX Installation and Connection Samsung Electronics • S-BOX Connection ① Input the video signal to the S-BOX. (Input terminal : HDMI, DP) ② Check the signal input from SOURCE STATUS.(RED : HDMI1 , GREEN : HDMI2, Blue : DISPLAY PORT) ③...
  • Page 62 8. S-BOX Installation and Connection Samsung Electronics ⑧ Instruction for handling HDBase-T cable ★ Orderly Rolled (Recommend) Random Rolled ★ (Not Recommend)  Do not use “comb” or “pinstripe” cable  Use HDBase-T cables with 15 meter long at minimum and 100 meter long at maximum.
  • Page 63 8. S-BOX Installation and Connection Samsung Electronics ⑧ Instruction for handling HDBase-T cable  EMI sources: Keep the cable away from electromagnetic interference environments such as high-voltage electrical cables, electric motors (such as elevators or refrigerators), fluorescent, light-fixtures and so on ...
  • Page 64 8. S-BOX Installation and Connection Samsung Electronics ⑨ Instruction for trimming HDBase-T cable on site.  STP RJ45 shielded Plug. RJ45 Connector should be CAT6 or CAT7 shielded RJ45 and load bar. Load bar  Insert conductors into the plastic loader : Using the standard wiring scheme shown here (T-568B), insert the conductors into the plastic loader piece of the R-J45 connector.
  • Page 65 8. S-BOX Installation and Connection Samsung Electronics ⑩ Instruction for trimming HDBase-T cable on site.  Slide the plastic loader down the cable : Slide the plastic loader down the cable as close to the base as possible.  Cut all conductors Using the wire cutters, cut all conductors leaving approximately 0.5” remaining.
  • Page 66 8. S-BOX Installation and Connection Samsung Electronics ⑩ Instruction for trimming HDBase-T cable on site.  Flip the drain wire up onto the RJ-45 connector Flip the drain wire up onto the RJ-45 connector. Clamp the strain relief down on the purple jacket of the BC-HDKat6a cable using the pair of pliers.
  • Page 67 8. S-BOX Installation and Connection Samsung Electronics • S-BOX Connection (Redundancy) ① If Redundant Spec should be used, Connect from DATA IN port of Interface Gender to DATA OUT port of the last cabinet by using OCM Cable. Last cabinet...
  • Page 68 8. S-BOX 설치 및 연결 Samsung Electronics • S-BOX Connection (External IR Receiver) ※ Only one external IR receiver is provided for a set. - External IR receiver can be connected to S-BOX body or InterfaceGender Card(I/G Card). ※ When connected to the I / G card, it must be in System - Power Control - Network Standby - On state.
  • Page 69 • S-BOX Connection (Panel Configuration) ① S-Box Picture Setting according to model • The default picture configurations are optimized for LH015IFH in Samsung factory. • The picture configurations will be configured automatically when you finish the installation. • For the best picture quality, Please connect S-Box and LED displays via LSM software properly.
  • Page 70 8. S-BOX Installation and Connection Samsung Electronics • S-BOX Connection (Grouping) ① Enable S-Box Grouping Home → Video Wall : OFF → On  [Cautions!!] Setup supported resolution for grouping before the grouping function of multi s-box is run by LSM.
  • Page 71 8. S-BOX Installation and Connection Samsung Electronics ③ Setup the resolution of input PC  PC: Click the right button of mouse → Click Screen resolution → Click Advanced settings  Click “Monitor” tap → Monitor Settings → Setup “Screen refresh rate” to 60Hz...
  • Page 72 8. S-BOX Installation and Connection Samsung Electronics ④ Supported resolution for S-box grouping (1/2)
  • Page 73 8. S-BOX Installation and Connection Samsung Electronics ④ Supported resolution for S-box grouping (2/2)
  • Page 74 8. S-BOX Installation and Connection Samsung Electronics ⑤ Picture menu setting  Both “Dynamic Contrast” and “Black Tone” should be off when using S-Box Grouping, since it may causes a color difference between S-Box.  Menu → Picture → Advanced Settings, - Dynamic Contrast : default “Medium”...
  • Page 75 8. S-BOX Installation and Connection Samsung Electronics • S-BOX Connection (Service port) ① The service port is dedicated port for monitoring to check the usage of OSD and the source being played at the initial installation of the S-BOX ②...
  • Page 76 7. S-BOX Installation and Connection Samsung Electronics • Turn on Simple wall mode  Simple wall mode is a wall paper function for end customer who don’t want to leave the Wall is black screen while in off status.  If the Wall screen resolution is covered in a S-box, turn on Simple wall mode in Factory mode.
  • Page 77: Settings And How To Use

    9. Settings and How to Use Samsung Electronics 9-1. Control Program for PCs LSM(LED Signage Manager) LSM Download Path : GSBN - SLM - Display solution download -> "LED SIGNAGE MANAGER" or "LSM“ • - GSBN : http://v3.samsunggsbn.com/ep...
  • Page 78 9. Settings and How to Use Samsung Electronics 9-1 Control Program for PCs Network IP Setting Tool Execute : [Start] – Program – Samsung – LED Signage Manager – Network Configuration Connect PC and Sbox with RS232C Cable, select connected SerialPort(COM*). And click “open” button.
  • Page 79 9. Settings and How to Use Samsung Electronics 9-1 Control Program for PCs LSM(LED Signage Manager) Software that adjusts the LED Cabinet Layout in Remote • S-box Ethernet PC and S-box should be connected through Ethernet connection. HDBT Control PC...
  • Page 80 9. Settings and How to Use Samsung Electronics 9-1 Control Program for PCs LSM(LED Signage Manager) Start– Login Page • If the LSM gets operated for the first time, the page to set the password will appear. To set the password, users have to input the same password two times and then click the “Start”...
  • Page 81 9. Settings and How to Use Samsung Electronics 9-1 Control Program for PCs LSM(LED Signage Manager) New Connection • To add connection information, you can either use Search function or input the IP address by yourself. If you click on the Search button, the IP addresses available on S-BOX in the same network will appear.
  • Page 82 9. Settings and How to Use Samsung Electronics [★ Cautions!] Recommend to use static IP address for the LED devices. If DHCP is used, IP address is changed automatically and LSM can be 9-1 Control Program for PCs disconnected. The 192.168.10.x band is used for internal communication of the LED Cabinet.
  • Page 83 9. Settings and How to Use Samsung Electronics 9-1 Control Program for PCs [★ Cautions!] LSM(LED Signage Manager) The network port 1515 and 48485 are used for internal communication between S-BOX and LED Cabinet. It should be include the firewall or network exception if customer used secured network.
  • Page 84 9. Settings and How to Use Samsung Electronics 9-1 Control Program for PCs LSM(LED Signage Manager) Main Window-Home Window • Input source: Input source, resolution, connection time of S-BOX are shown. Cabinet Layout : Layout, number of units, number of connections and number of disconnections in all LED cabinets are shown.
  • Page 85 9. Settings and How to Use Samsung Electronics 9-1 Control Program for PCs LSM(LED Signage Manager) Main Window-Edit Connection Layout Window • Connection layout: The location and the layout of each LED cabinet are adjusted in the output source area of the S-BOX.
  • Page 86 9. Settings and How to Use Samsung Electronics 9-1 Control Program for PCs LSM(LED Signage Manager) Main Window-Connection Window • Device connection list view: Check S-BOX composition, modify and delete S-BOX connection, show by each LED Cabinet Group Connection layout (View Port):...
  • Page 87 9. Settings and How to Use Samsung Electronics 9-1 Control Program for PCs LSM(LED Signage Manager) Main Window-Connection Window - Device Information/Setting View • 1. Basic : . Power On/Off, Change input source, Screen Mute / Freeze , Menu Size 2.
  • Page 88 9. Settings and How to Use Samsung Electronics 9-1 Control Program for PCs LSM(LED Signage Manager) Main Window-Connection Window - Device Information/Setting View • 6. Cabinet Settings . LOD, Pixel RGB Data, Backlight . Software Update function (FPGA, Calibration data, etc.)
  • Page 89 9. Settings and How to Use Samsung Electronics 9-1 Control Program for PCs LSM(LED Signage Manager) Main Window-Connection Window - Sub Information View • Monitor Window: Checking MDC communication log and connected device information available, able to be extracted via file...
  • Page 90 9. Settings and How to Use Samsung Electronics 9-1 Control Program for PCs LSM(LED Signage Manager) Main Window-Preference • Options number of times the command retried interval of checking error status alarm temperature warnings Support program language Log data management...
  • Page 91 9. Settings and How to Use Samsung Electronics 9-1 Control Program for PCs LSM(LED Signage Manager) Dehumidification using LSM • Dehumidification button is located in S-Box menu When you click the button, dehumidification starts You can see how long it takes...
  • Page 92 9. Settings and How to Use Samsung Electronics 9-2. Color Calibration On-Site Calibration Measurement Device Target Type Service Type Development Schedule Colorimeter (CA310 / CA410 / etc) Stamp / Module / Install / Maintenance 2019 March Cabinet Mobile (Smart Phone) On-Site Calibration Engineer Version S/W Using Colorimeter - Add &...
  • Page 93: Issue And Solution

    10. Issue and Solution Samsung Electronics Problem Case 1 Rule 1: The 1 Cabinet from I/G board must be ID #2 for the LSM Setup Rule 2: The 1 Cabinet from I/G board must be set as Master. The 2 Master cabinet is not allowed for the LSM connection.
  • Page 94: Cable Connection

    10. Issue and Solution Samsung Electronics  S-Box Network Connection Issue with LSM ① When you can‘t find S-Box or see disconnected message in LSM -. Check Ethernet cable connection -. Check IP setting of S-Box -. Check target IP of S-Box in LSM -.
  • Page 95 10. Issue and Solution Samsung Electronics Problem Case 2 Rule 1: The 1 Cabinet from I/G board must be ID #2 for the LSM Setup Rule 2: The 1 Cabinet from I/G board must be set as Master. The 2 Master cabinet is not allowed for the LSM connection.
  • Page 96 10. Issue and Solution Samsung Electronics How to do Factory Reset After checking cable connection order, the cabinet which is not display the proper picture position will be Wrong positioned Master cabinet. In this case, Do factory reset to change to slave cabinet .
  • Page 97: Bezel Installation

    11. Bezel Installation Samsung Electronics • Installing Frame Bezel 1. Attach ASSY FRAME-BEZEL SIDE to the cabinet. • Check for allowable gaps for the each FRAME-BEZEL SIDE. • If it needs to adjust gaps, it can be adjusted by attaching or detaching GAP SHEET on the magnets.
  • Page 98 11. Bezel Installation Samsung Electronics 2. Use SCREW(M3,L5) to fasten the BRACKET LINK to the right side of the FRAME-BEZEL TOP BOTTOM. M3,L5 BRACKET CENTER...
  • Page 99 11. Bezel Installation Samsung Electronics 3. Place the ASSY FRAME-BEZEL TOP BOTTOM to the top left of the cabinet. • Align the FRAME-BEZEL SIDE and FRAME BEZEL TOP BOTTOM to ensure there is no gap between them. • Use 2 SCREW (M3, L5) to fasten the left side of the FRAME BEZEL TOP BOTTOM to the FRAME BEZEL SIDE.
  • Page 100 11. Bezel Installation Samsung Electronics 4. Place the FRAME-BEZEL TOP BOTTOM to the top right of the cabinet. • Align the FRAME BEZEL SIDE and FRAME-BEZEL TOP BOTTOM to ensure there is no gap between them. • Use 2 SCREW (M3, L5) to fasten the right side of the FRAME-BEZEL TOP BOTTOM to the FRAME BEZEL SIDE.
  • Page 101 11. Bezel Installation Samsung Electronics 5. Use 2 SCREW (M3, L5) to fasten the left side of the FRAME-BEZEL TOP BOTTOM. [Fig.1] 6. Use 6 SCREW (M4, L8) to fasten the FRAME BEZEL TOP BOTTOM to the screw holes on the cabinet. [Fig.2]...
  • Page 102 11. Bezel Installation Samsung Electronics 7. Repeat steps 2-6 to install the cabinet bottom. * Make sure that there is no gap between the FRAME BEZEL SIDE and FRAME BEZEL TOP BOTTOM units on both ends. M3,L5 M3,L3 M4,L8 M4,L8...
  • Page 103 11. Bezel Installation Samsung Electronics • Extending the FRAME BEZEL Extending vertically • Connect FRAME-BEZEL LEFT & RIGHT for over 5~8 cabinets high M3,L3...
  • Page 104 11. Bezel Installation Samsung Electronics • Extending the FRAME BEZEL Extending side by side * Follow the basic installation steps and the below guidelines. • Extending 6 cabinets side by side Connect 3 FRAME BEZEL TOP BOTTOM units. Fastening with...
  • Page 105 Reference – Module Attachment Principle Samsung Electronics Section view HOLDER-MAGNET It is possible to adjust height by using driver. (4points / module) => Return in a LED MODULE counterclockwise direction. (1mm/1rotation) BRACKET-SUB BRACKET MAGNET LED MODULE MAGNET BRACKET SUB HOLDER-MAGNET...
  • Page 106 Reference – How to separate Module Samsung Electronics < Edge protection > Disassemble Cover-PCB Attach Protection Make gap (move module 2mm ) Separate Module with Magnet jig Full Protection Module for change Magnet Magnet in protection Stud in module section...
  • Page 107 - Appendix ※ Certified Cable by HDbaseT Samsung Electronics ★ For HDBT signal stability, do not use CAT5E cables even though the cables are included in the following list Vendor Model Name Vendor Model Name HNCPRO(TM) HOME NETWORK CABLE Trends Electronics...
  • Page 108 - Appendix ※ Certified Cable by HDbaseT Samsung Electronics ★ For HDBT signal stability, do not use CAT5E cables even though the cables are included in the following list Vendor Model Name Vendor Model Name Kramer Electronics BC-HDKat6a Snap AV...

Table of Contents