Huawei RRU3269 Installation Manual page 52

Hide thumbs Also See for RRU3269:
Table of Contents

Advertisement

RRU3269
Installation Guide
2.
(1) Lifting sling
Do not remove the stretch sling and protection pipe or bind optical fibers using one sling, as
shown in Figure 7-8.
Issue Draft B (2018-05-15)
Installation engineer B places the fiber coiler for coiling optical fibers on the fiber spools,
and installation engineer D lead the lifting sling through the stretch sling of the optical
fibers and use the other sling as a traction sling to secure the cables 4 m (13.12 ft) away
from the lifting sling, as shown in Figure 7-7.
Figure 7-7 Binding optical fibers
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
7 Hoisting an RRU and Related Cables onto a Tower
(2) Stretch sling
(3) Traction sling