Huawei RRU3269 Installation Manual page 116

Hide thumbs Also See for RRU3269:
Table of Contents

Advertisement

RRU3269
Installation Guide
Issue Draft B (2018-05-15)
Figure 9-19 Installing an RRU AISG extension cable
e.
Waterproof the joint of the AISG multi-wire cable and AISG extension cable.
Before wrapping waterproof tape, stretch the tape evenly until the length of the tape becomes twice
its original length.
Do not stretch the PVC insulation tape when wrapping the PVC insulation tape.
Wrap each layer of tape around the connector tightly and neatly, and ensure that each layer of tape
overlaps more than 50% of the preceding layer. Ensure that neighboring layers are stuck to each
other.
Ensure that the adhesive surface of the tape overlaps the lower layer.
When cutting off the cable ties, reserve a redundant length of 3 mm (0.12 in.) to 5 mm (0.2 in.).
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
9 Installing RRU Cables
108