System Set-Up:

Set system on a dry, level surface.
1. Obtain appropriate protective equipment.
2. Attach hose to machine outlet using a hose clamp.
3. Open slide gate & place pin in desired opening.
4. Connect 12 gauge heavy duty power cords; each power source is required to be an
independent circuit. LED lights will glow indicating power to
agitator and blower(s) circuit breakers. Note: If cannot find 3
independent circuits, or desire is to use 1 blower vs. 2 blowers,
then do not need to connect the second blower (i.e. only 2
independent circuits required).