SUN2000-(3.8KTL-11.4KTL)-USL0
User Manual
6.1 Checking Before Power-On
Table 6-1 Checklist
No.
1
2
3
4
5
6
7
8
9
10
11
12
Issue 01 (2018-05-21)
6
Check Item
SUN2000 installation
Antenna installation
SIM card installation
Cable layout
Cable tie
Grounding
Switches
Cable connections
Unused terminals and ports
Cable routing pipe sealing
Cleanliness in the maintenance
compartment
Installation environment
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
System Commissioning
Acceptance Criteria
The SUN2000 is installed correctly,
securely, and reliably.
The antenna is installed correctly, securely,
and reliably.
The SIM card is installed correctly, securely,
and reliably.
Cables are routed properly as required by the
customer.
Cable ties are secured evenly, with no sharp
protrusions.
The ground cable is connected correctly,
securely, and reliably.
The DC switch and all the switches
connecting to the SUN2000 are in the OFF
position.
The AC output power cable, DC input power
cable, battery cable, and signal cable are
connected correctly, securely, and reliably.
Unused terminals and ports are fitted with
waterproofing bolts or watertight caps.
All cable routing pipes at the bottom of the
enclosure are sealed.
The maintenance compartment interior is
clean and tidy.
An appropriate installation space has been
6 System Commissioning