Figure 5-10 SUN2000-9KTL/10KTL/11.4KTL-USL0 (L1/L2)
----End
Connecting the AC Output Power Cable for Critical Load
Step 1 Install the pipe fittings. For details, see
Step 2 Route the AC output power cable through the conduit and then the fitting of the pipe.
Step 3 Connect the AC output power cable to the terminal block.
Step 4 Secure the fitting to the conduit.
Step 5 Check that the cables are connected correctly and securely. Then take appropriate measures to
ensure that the pipe conduit and fitting are secured reliably, and seal the cable holes.
Step 6 Keep the maintenance compartment clean.