Basic Heating Piping Arrangements; Boiler Pump Air Bleeding; Primary/Secondary Piping - Benefits And Installation Rules - IBC DC Series Installation And Operating Instructions Manual

Boilers / water heaters
Hide thumbs Also See for DC Series:
Table of Contents

Advertisement

WARNING
Do not use automotive-
type ethylene or other
types of automotive glycol
antifreeze, or undiluted
antifreeze of any kind. This
may result in severe boiler
/ water heater damage. It
is the responsibility of the
Installer to ensure that glycol
solutions are formulated to
inhibit corrosion in hydronic
heating systems of mixed
materials. Improper mixtures
and chemical additives may
cause damage to ferrous and
non-ferrous components as
well as non-metallic, wetted
components, normally found
in hydronic systems. Ethylene
glycol is toxic, and may be
prohibited for use by codes
applicable to your installation
location. For environmental
and toxicity reasons, IBC
recommends only using non-
toxic propylene glycol.
1-24
DC SERIES BOILERS / WATER HEATERS DC 15-95, DC 15-96, DC 20-125, DC 33-160

1.6.2 Basic Heating Piping Arrangements

PRIMARY / SECONDARY PIPING - BENEFITS AND INSTALLATION RULES
1.
Good circulating water flow through the boiler irrespective of load or radiation
system head
Allows flexible ΔT° control in secondary loops
2.
Adds to the system's thermal buffering, to assist in handling small loads and
3.
temperature transition.
A Primary / Secondary piping configuration requires an extra pump, independant
from any secondary load pumps. The DC series modulating boiler / water heater
includes the boiler Primary Pump installed inside the boiler / water heater cabinet
and is pre-wired. The pump's volute is epoxy coated to allow compatibility with
the non-oxygen barrier tubing found in some older radiant heating systems.
For optimal performance, place pumps on the supply side of secondary loops
to facilitate air evacuation. Use pumps with internal check valves to avoid ghost
flows and thermal siphoning.
The DC series boilers are designed to be piped in a Primary/Secondary piping
arrangement. In some cases the boiler can be piped in series with the heating
load if the boiler's pump is capable of providing the flow and head the system
requires. For example a DC series boiler and an IBC Air Handler series can
be installed together without the use of an additional pump if the air handler is
installed within close proximity of the boiler and with properly sized supply and
return piping (see Figure 29a).
Propylene Glycol mixtures of 25% - 50% are acceptable for use within the
boiler and piping system. In general, the use of propylene glycol will reduce the
heating capacity of the heating system and increases the pump head required for
adequate boiler / water heater flow.
If the installation involves small loads, as in typical zoned baseboard heating
applications, use of a buffer tank is recommended. To aid in temperature
transition from hot to cool loads, a 3-way mixing valve can be placed at the
entrance to the cool load (this will also provide floor protection). This will permit
immediate circulation of mixed flow into the cool loop.

1.6.3 Boiler Pump Air Bleeding

After filling the boiler for the first time, bleed any air trapped in the boiler pump.
An absorbent cloth should be placed beneath the large slotted screw in the
center of the pump. Turn this screw counter-clockwise until water drips from
behind it and air is purged. Reseal the screw, but do not over-tighten.
INSTALLATION AND OPERATION INSTRUCTIONS

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Dc 15-96Dc 33-160Dc 20-125Dc 15-95

Table of Contents