5.5 Anchoring points for handling

We recommend the use of shackles when handling these units.
These lifting lugs are used when placing blocks near each other, and must not be used once disassembled.

5.6 Storage

ƒ Do not remove the original packaging.
ƒ Do not remove the protective caps until you are ready to connect the coils.
ƒ The unit must be stored on a flat surface.
ƒ Fit protection against shocks or impacts, which could damage the unit or its accessories.
ƒ Store the blocks in their packaging, in a dry area sheltered from the weather.
ƒ The ambient temperature must be between -10°C and
50°C.
ƒ To facilitate the assembly of multisplit units, their
components must be kept in the relevant groups. Refer
to the dimensional drawings and marker labels on each
block (see opposite).
: Acknowledgement of receipt number.
: Block markings.
A1, A2, ....A9: multi-section unit.
A second unit will be marked B1, B2,.... B9.
The numbers 1, 2 and 3 do not necessarily indicate the order
of assembly (refer to the dimensional drawing).
: Internal production order = The serial number should be
quoted in all correspondence.
: Internal designation.
: Customer name.
: Pre-shipping internal inspection.
: Customer reference.
: Weight of corresponding block.
: Block year of manufacture.
: Manufacturer's name and address.

6 - INSTALLATION

6.1 Warning

The installation of equipment must comply with the regulations in force at the installation site.
Warning!
Follow the safety instructions in § 2 - SAFETY INSTRUCTIONS

6.2 Selecting a location

ƒ Before setting up and connecting the unit, the installer must check the following points:
- The unit's earthquake resistance has not been verified.
- These units can be placed directly on flat, level ground. The flatness value must be the best possible, around one per
thousand.
-
For outdoor installation, take into account the regulations in force and the weather conditions at the installation site (risk
of snow, height from the ground, risk of wind, etc.).
- The selected location must not be liable to flooding.
- Raise the unit to ensure that the unit's operation is not affected by a buildup of snow.
- Take into account the required height of the siphon, the slope and the length of the condensate drainage container.
75
60
Ø 12.5
47
28
L
L
ORDER NUMBER
00001003
1
OF02376570
3
DESIGNATION:
4
5
CUSTOMER:
7
REFERENCE:
MASS
8
10
EN - 6
Ø 35
BLOCK
A1
Packing conformity
YEAR OF MANUFACTURE
2016
2
6
9

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents