28
Maintenance contents
Check the security
features

4.4.2 Maintenance guide

Cleaning the inverter:
1.
2.
3.
4. Repeat Section 4.1 operating content.
5.
Cleaning the fan (for AS-IC01-8000-2 and AS-IC01-10000-2)
1.
2.
3.
4. Remove the screws and covers of cooling bin or fan box, as shown in Figure 15A and 15B below.
Figure 15A: Disassembling the cooling bin
PD201809 AEG GRID-TIED THREE-PHASE SOLAR INVERTER (4-10 kW) V.2-18 EN
Check the off-on feature of inverter: use monitoring software
or LCD and keyboard on the inverter (if your model features
the latter two), turn "off" and "on", to confirm that the off-on
functionality is working correctly. At the same time, make
sure that the monitoring software can regularly
communicate with the inverter. Check the warning label
on/around the inverter, and replace it if necessary.
Disconnect the input and output switches.
Wait for ten minutes.
Use a soft brush or a vacuum cleaner to clean the surface and the inlet and outlet of the inverter.
Restart the inverter.
Disconnect the input and output switches.
Wait for ten minutes.
Disassemble the inverter in the same process as the installation procedures described in section 4, but
in reverse order
Maintenance methods
Table 14: Maintenance actions
Maintenance cycle
Every six months
Figure 15B: Disassembling the fan box
28