Installing A Grounding Cable For The Bc8910A Cabinet - Zte RSU82 S1900 Hardware Installation

Table of Contents

Advertisement

Figure 7-11 Grounding Cable Routing of Stacked Cabinets
The grounding cable of the single cabinet is connected to a nearby outdoor grounding
busbar.

7.4.1 Installing a Grounding Cable for the BC8910A Cabinet

This procedure describes how to install the bus grounding cable of the stacked cabinets.
The bus grounding cable is connected to a nearby outdoor grounding busbar.
Prerequisite
l
The ESD wrist strap must be worn.
l
The tributary output of the power supply is cut off.
SJ-20150203110107-011|2016-03-23 (R1.1)
7-13
ZTE Proprietary and Confidential
Chapter 7 Cable Installation