Execution Of Work; Safety Markings - Eaton Power Xpert UX 12 User Manual

With w-vaci circuit breaker (up to 24 kv) air insulated medium-voltage switchgear
Table of Contents

Advertisement

2.3.3

Execution of work

ALWAYS check that the equipment is dead.
Fit suitable earthing.
NEVER approach an unearthed installation.
Ensure maintenance work is carried out timely, in
accordance with the instructions in this manual
Replace worn and/or damaged parts only with original
Eaton spares or spares approved by Eaton.
Take the following minimum precautions when carrying
out work:
Working on live or partly live installation:
Clearly indicate the working area.
Make sure that the installation is clean and dry; check
for leakage paths where voltage could track to the
outside.
Fit earthing to the panel, which is being worked on;
only operate on earthed panels.
Always check that the part that is being worked on is
dead.
Working on a dead installation:
Fit earthing; work on earthed panels only.
Always check that the system is dead.
When re-commissioning:
Check that all the work in the immediate area has
been completed.
Check (if necessary) that all related work in other
areas has been completed.
Check the safety of all personnel concerned.
Remove safety earthing and other safety provisions.
2.3.4

Safety markings

These signs further indicate possible dangers:
Dangerous electrical voltage
Electrical safety earth
WARNING
®
Power Xpert
UX with W-VACi circuit breaker 6063308 G01 01 14 July 2011 www.eaton.com
Product description
21