Takara Belmont Yume Oasis Installation Instructions Manual page 7

Advertisement

[Form]
Mortar Base
4 Installation of mortar base
Install mortar base.
5 Removal of form, Installation of bury frame, and Installation of mortar base
1. Remove the form, and then install the bury frame of floor unit to the position where marked in Step 2.
※ Please use our standard bury frame as a bury frame. (optional)
※ Attach the white top of bury frame to the top face of the Mortar finish level (★).
【Wall thickness: EA-OAFWYM (optional item)】
※ Floor units installed into the bury frame.
(After the bury frame is installed and the floor is completely finished, the floor unit is installed.)
Cut off three portions
according to pipe positions.
Form
Bury frame
For bottom-strength when install the floor unit,
pour the mortar into the whole of the bottom space.
Reinforcement Crosspiece
Damp-proof Sheet
Wall thickness t=18㎜
※ When installing the floor unit, fine adjustment
will be required.
Be sure to install in the following order:
(1) Install a form and install mortar base.
(2) Install a bury frame and install mortar filling.
Mortar base
Surely attach the top of bury frame
to the line marked ★.
F.L
Pipe
CAUTION
● Do no remove the reinforcement crosspiece until the mortar filling is
dried. The bury frame may bend and prevent the resin case of floor unit
from fitting.
● Do not remove the damp-proof sheet.
It prevents the moisture of mortar from entering the floor unit.
7
F.L
(Mortar finish level)
Pipe
CAUTION
If floor panels are not laminated but the
floor is finished with mortar,
it is always required that the top end of
the mortar work form is also finished with
mortar.
Mortar finish thickness
F.L