Installing the System into the Rack

After the rails are installed on the chassis and on the rack, the server can be installed in the
rack. Be sure to use sufficient personnel to lift it safely.
Installing the Chassis into a Rack
1. Pull the middle rail out of the front of the outer rail and make sure that the ball bearing
shuttle is locked at the front of the middle rail.
2. Align the inner rails on the chassis with the front of the middle rails and then push
evenly on both sides of the chassis. When partially in, the locking levers will stop further
progress.
3. Press down the locking levers on the inner rails and push the chassis all the way into
the rack. The front latches will click into place.
Note: Figure is for illustrative purposes only. Always install servers to the bottom of a rack first.
Note: Confirmation of the installation of this equipment is confirmed with a universal pitch rack.
(EIA-310D)
1
2
Figure 2-5. Installing the System into the Rack