16 Unplug the stock O2 sensor connectors (Fig. M).
These connectors are located on the right side of the motorcycle towards the front
of the frame.
17 Plug the supplied Dynojet O2 Optimizers into the stock wiring harness
(Fig. N).
The stock O2 sensors will no longer be connected to anything and can be
removed if desired.
18 Install the PCV underneath the left hand side cover (Fig. O).
19 Attach the ground wire of the PCV to the negative (-) side of the battery.
20 Reinstall the bodywork.
2016 Triumph T120 PCV - 7