Connecting the Dual Detector Microfluidics

Thermo Scientific
Figure 3.
Kit Schematic Diagram: Two GC Detectors
GC Detector
GC Detector
60 cm long; 170 um i.d.
To connect the dual detector microfluidics to the TRACE 1300/1310 GC
1. Cool the oven, injector or injectors, transfer line, ion source, and any installed GC
detectors to room temperature and shut down the GC.
WARNING - BURN HAZARD: The injectors, detectors, oven, and transfer line may be hot.
Allow them to cool to room temperature before touching them.
2. Push down on the power switch to power off the GC.
3. Shut down the TSQ 8000 or ISQ mass spectrometer using the software. See your mass
spectrometer's user guide for more information. The heaters and the turbo-molecular
pump power off.
Figure 4.
Finding the Vent Valve on the Mass Spectrometer
Vacuum Interlock Shield
Dual Detector Microfluidics Installation Guide
GC Injector
Column
Vent Valve Knob
Dual Detector Microfluidics Installation Guide
Connecting the Dual Detector Microfluidics
Power Switch