Finishing

A. Facing Material
• Metal front faces may be covered with non-combustible
materials only.
• Facing and/or finishing materials must not interfere
with air flow through louvers, operation of louvers or
decorative fronts, or access for service.
• Facing and/or finishing materials must never overhang
into the glass opening.
• Observe all clearances when applying combustible
materials.
• Confirm that appliance is plum, square and level. See
Section 6.
• Seal joints between the finished wall and appliance top
and sides using a 300 ºF minimum sealant. Refer to
Figure 10.1
WARNING! Risk of Fire! DO NOT apply combustible
materials beyond the minimum clearances. Comply with
all minimum clearances to combustibles as specified in
this manual. Overlapping materials could ignite and will
interfere with proper operation of decorative fronts and
louvers.
FACING MATERIAL UP TO 1/2 IN. THICK
MAY BE COMBUSTIBLE - TOP AND SIDES
DRYWALL SUPPORT
3 IN.
1 IN.
0 IN.
HIGH TEMPERATURE (300º F / 149º C MIN.)
TOP & SIDE SEAL JOINT
Figure 10.1 Facing Materials
0 IN.
1 IN.
0 IN.
Heat & Glo • SL-5, SL-7, SL-9 Installation Manual • 2392-980 Rev. L • 6/17
NOTICE: Surface temperatures around the appliance will
become warm while the appliance is in operation. Ensure
finishing materials used for all surfaces (floor, walls,
mantels, etc.) will withstand temperatures up to 190°F.