13

Finishing

A. Mantel and Wall Projections
WARNING! Risk of Fire! Comply with all minimum clear-
ances as specified. Framing closer than the minimums list-
ed must be constructed entirely of noncombustible materials
(i.e., steel studs, concrete board, etc.)
Note: No mantels allowed when using Tonic or
Studio fronts.
Combustible Mantels
NON-COMBUSTIBLE
BOARD
10,2
7,6
5,1
TOP FRONT EDGE
Note: All measurements in centimeters.
Note: Measurement is taken from top of the opening,
NOT the top of the fireplace.
Figure 13.1 Minimum Vertical and Maximum Horizontal
Dimensions of Combustibles
Combustible Mantel Legs or Wall Projections
TOP VIEW
33 cm
MINIMUM
Figure 13.2 Combustible Mantel Leg or Wall Projections
(Acceptable on both sides of opening)
WARNING! Risk of Fire! DO NOT apply combustible mate-
rials beyond the minimum clearances. Comply with all mini-
mum clearances to combustibles as specified in this manu-
al. Overlapping materials could ignite and will interfere with
proper operation of doors and louvers.
58
30,5
27,9
25,4
22,9
20,3
17,8
15,2
12,7
25,4
22,9
20,3
17,8
15,2
12,7
10,2
7,6
5,1
OF FIREPLACE
1,3 cm
MINIMUM
91,44 cm MAXIMUM
Heat & Glo • 350TSI-P-CEM • 2033-973 Rev. G • 4/17
B. Facing Material
• Metal front faces may be covered with non-combustible
materials only.
• Facing and/or finishing materials must not interfere with
air flow through louvers, operation of louvers or doors, or
access for service.
• Facing and/or finishing materials must never overhang into
the glass opening.
• Observe all clearances when applying combustible
materials.
• Seal joints between the finished wall and appliance top and
sides using a 300 ºF (149 ºC) minimum sealant.
30,5
27,9
A
350TSI-P-CEM
Figure 13.3 Noncombustible Facing Diagram
B