Safety
Rating
Mechanical
Information
Data
Installation
6.
Quick Start Commissioning
This procedure is written from default parameter settings as the starter would be delivered from the factory.
Always apply control voltage before (or with) mains voltage.
WARNING
6.1
Control wiring
Figure 6-1 Control terminals for basic connection
220-440 VAC +10%
-15%
110-210 VAC
For keypad control, the soft starter requires:
control supply connections (terminals CSH, CSL, CSR depending on the control voltage)
programmable input A (DI4, +24V) must be closed or Pr 3A Input A Function must be changed from Emergency Stop
Digistart IS User Guide
Issue: 4
Electrical
Keypad
Quick Start
Installation
and
Commissioning
Status
F1
CSH
CSL
+10%
CSR
-15%
DI1
+24V
DI2
+24V
DI3
+24V
DI4
+24V
E
www.controltechniques.com
Operation Programming Diagnostics Application
CSH-CSR or CSL-CSR
DI1, +24V
DI2, +24V
DI3, +24V
F1
Technical
Maintenance Options
Examples
Data
Control supply
Start
Stop
Reset
Fuse (optional)
35